Era Infra Engineering Ltd. v. NTPC Ltd.
Case brief
What is this about?
The petitioner sought an extension of the arbitration tribunal's mandate. The court granted the extension of 12 months, finding sufficient cause for the delay caused by NCLT pendency.
What did the court decide?
The mandate of the Arbitral Tribunal is extended by a period of 12 months from today; the period from 01.03.2024 till today is regularized.