Ssangyong Engineering and Construction Co. Ltd. v. National Highways Authority of India
Case brief
What is this about?
Petition filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of the arbitral tribunal's mandate. Court allowed the petition with consent of parties, extending the mandate for nine months.
What did the court decide?
Mandate of the arbitral tribunal extended for a period of nine months with effect from 14.08.2024.