M/S Cobra Instalaciones Y Servicios, S.A & M\S Shyam Indus Power Solution Pvt. Ltd.(Jv) v. Haryana Vidyut Prasaran Nigam Ltd.(Hvpnl)
Case brief
What is this about?
Appeal against a Section 34 judgment reversing an arbitral award refunding 50% of liquidated damages for delay in a power project. The Division Bench held the arbitrator's rough-and-ready quantification was evidence-based and not perverse, restored the award on liquidated damages, and held a Section 34 court cannot relegate parties to re-agitate disputes before the tribunal.
What did the court decide?
Impugned judgment set aside; award restored qua liquidated damages; J.V. Company entitled to refund of 50% of L.D. retained by HVPNL with interest per the award.