Mf Buildcon Pvt. Ltd. v. Anjali
Case brief
What is this about?
In an appeal against the dismissal of an execution petition seeking specific performance, the Delhi High Court held that the Appellant failed to pay the balance consideration by the agreed date. Upholding the Single Judge, the Court refused to extend time under Section 28 of the Specific Relief Act due to the Appellant's conduct and forced possession.
What did the court decide?
The appeal was dismissed and the Single Judge's judgment rescinding the settlement agreement was upheld.