Sharma& Asssociates,Contractor.Pvt Ltd. v. Progressive Construction Ltd. & Anr.
Case brief
What is this about?
Objections under Sections 30 and 33 of the Arbitration Act, 1940 to an award on a Tanakpur hydroelectric project sub-contract were dismissed. The court held challenges went only to merits and factual appreciation, beyond permissible interference; all awarded claims were supported by cogent reasons.
What did the court decide?
Defendant's objections dismissed; arbitral award dated 20.03.2015 made into order of the Court.