Ranjit Construction Company v. Gujrat State Road and Building Deprtment & Ors.
Case brief
What is this about?
Section 9 arbitration petition withdrawn after appointment of a sole arbitrator, with liberty to move the arbitrator under section 17; interim relief granted earlier continued until the arbitrator takes a view.
What did the court decide?
Petition withdrawn; liberty to apply under s.17 before arbitrator; interim relief of order dated 09.12.2022 to continue until arbitrator decides.