Hule Constructions Pvt. Ltd. v. National Highway Authority of India & Ors.
Case brief
What is this about?
The Court appointed a sole arbitrator to adjudicate disputes under a NHAI contract, holding the Authority's unilateral appointment power invalid. The Section 9 petition was disposed of by directing the parties to seek interim relief before the appointed arbitrator under Section 17.
What did the court decide?
Appointment of Mr. Nikhil Mehra as Sole Arbitrator; disposal of petition directing interim relief to be sought before Arbitrator.