Dharambir Sandhu v. Union of India through General Manager, Northern Railways and Anr.
Case brief
What is this about?
This Court granted the petitioner's application under Section 11 of the Act to appoint an arbitrator. Rejecting the respondent's plea that the dispute was non-arbitrable due to a 'No Claim Certificate,' the Court appointed Mr. Bhuvnesh P. Khare as sole arbitrator. The arbitration is to be conducted under the Delhi International Arbitration Centre rules, with all contentions regarding arbitrability
What did the court decide?
Appointment of Mr. Bhuvnesh P. Khare as sole arbitrator; arbitration to be conducted under DIAC rules.