Dharamvir and Co. v. Delhi Development Authority
Case brief
What is this about?
Petition under section 11 of the A&C Act seeking appointment of an arbitrator for disputes with DDA arising from an agreement dated 26.09.2011. The court found a valid arbitration agreement and territorial jurisdiction, waived costs imposed on the respondent, and appointed a sole arbitrator under DIAC's aegis.
What did the court decide?
Sole arbitrator (Ms. Suditi Batra) appointed; arbitration to proceed under DIAC aegis; costs of Rs. 25,000/- on respondent waived.