Avm Oil Field Services v. Gail Gas Limited
Case brief
What is this about?
High Court held that the petitioner's right to challenge a banning order under contract clause 45 excludes arbitration, so the impugned order is not liable to be quashed merely due to pending arbitration proceedings.
What did the court decide?
Writ petition dismissed; liberty granted to petitioner to file an appeal under Clause 39F of the ITB before the Appellate Authority with liberty to seek appropriate action in accordance with law.