28.3.4 This is noted that the work was awarded such that, the date of start Itself falls at the start of the rainy season, though, the tender for the work was received as early as In; Dec, 2012 with the bids to remain valid for 90 days only. Such long period of delay in awarding the work Is abnormal. Therefore, the Respondents cannot absolve themselves of the responsibility of bringing the period of execution of work during rains. Similarly, the contract stipulates, approval of design mix by CRRI or such organization. The Respondents again cannot absolve themselves of the responsibility of delay by CRRI which is a government organization like that of the Respondents and Respondents were in good position to get this expedited. The initial delay in award of work has also resulted into bringing the work running into extreme cold weather of winter season. Since the work is predominantly bituminous work which is not advisable to be executed during extreme cold weather and the period has rightly been allowed by the Respondents as a genuine delay. In view of this, it is considered that the Claimants need to be partly compensated for extra expenditure on overheads for the part of the period other than the period of delay due to extra work.”