What is this about?
The Court set aside part of an Arbitral Award under Section 34 of the Arbitration Act. Claim No.1 was upheld interpreting contract conduct regarding price variation. Claim No.2 was disallowed as it was based on no evidence despite the Tribunal's direction for joint measurement.
What did the court decide?
Claim No.1 allowed; Claim No.2 allowed to the extent of the Arbitral Tribunal's direction for joint measurement was set aside and the claim disallowed due to lack of evidence.