MCH Dispensary was operating and the bath rooms attached thereto; the staff and doctors of the MCH Centres did not allow the work of chiseling and removal of plaster etc. to be carried out while the Dispensary was functional; (iv) that the petitioner vide letters dated 13th March, 2013, 11th April, 2013, 26th April, 2013, 7th May, 2013 and 27th May, 2013 informed the respondents EDMC of the hindrance in execution and the slow progress of the work; (v) after much persuasion, fourth site was handed over but the progress of the work still remained slow; (vi) the respondents EDMC however issued a notice dated 11th March, 2013 asking the petitioner to show cause why action under Clause-2 of the Agreement be not taken against the petitioner on account of breach of contract on the part of the petitioner in having not even started the work by then though the time for completion thereof was of nine months only; (vii) the said show cause notice was mala fide and a counterblast to the letter dated 13th March, 2013 of the petitioner complaining of the delays on the part of the respondents EDMC and as is also evident from the fact that the same was issued much prior to the stipulated date of 23rd November, 2013 of completion of the work; (viii) the petitioner vide its letter dated 1st July, 2013 replied to the show cause notice and also met the Chief Engineer on the same day and was made to