Shambhavi Contractors (Pvt.) Ltd. v. M/S National Buildings Contruction Corporation Limited and Ors.
Case brief
What is this about?
Petitioner sought quashing of contract termination citing delays caused by respondents. Court held petition barred by long delay, laches, and serious disputed questions of fact involving third-party rights.
What did the court decide?
Writ petition and accompanying application dismissed without interference as delay was unreasonable and third-party rights created.