M/S Rajendra Kumar Poddar v. State of Chhattisgarh
Case brief
What is this about?
A contractor sought refund of excess GST payable after the works-contract GST rate rose from 12% to 18% with effect from 18.07.2022. The court disposed of the petition by directing respondents No.2 and 3 to decide the pending representation within 90 days, taking into account similar decisions taken for other State departments.
What did the court decide?
Respondents No.2 & 3 directed to consider the representation dated 30.11.2023 within 90 days.