Mahendra Kumar Nathhani v. State Of Chhattisgarh and Ors.
Case brief
What is this about?
Chhattisgarh High Court, Bilaspur – WPC No. 861 of 2015, decided 08/11/2024 by Bibhu Datta Guru, J. (NAFR). Keywords: Section 24(2) RFCTLARR Act 2013 lapsing; Land Acquisition Act 1894 award dated 10.05.2013 in L.A. Case No. 13/A82/2011-12; compensation Rs. 8,00,397/- paid on 06.01.2014 vide Cheque No. 296239; possession handed over to Defence Estate Officer, Jabalpur on 06.01.2014; village Tilsara, Tehsil Bilha, District Bilaspur; acquisition for Department of Defence; plea of non-taking of physical possession rejected; writ petition dismissed. Relevant where compensation and possession were both completed, defeating a Section 24(2) lapsing claim.
What did the court decide?
Since the petitioner himself handed over possession of the land to the Estate Officer, Department of Defence, Jabalpur through the Land Acquisition Officer on 06/01/2014 and compensation was also paid on 06/01/2014, the contention that physical possession had not been taken fails and Section 24(2) of the 2013 Act is not attracted or applicable.