taken as provided in sub clause 2(ii). Under this clause, as is clear from the reading thereof, the Department had a right to cancel the contract and withhold the agreement. That has been done. The Department has also a right to get the job which was to be carried out by the defaulting contractor, to be carried out from other contractor(s). In such an event, the Department also has a right to recover the difference from the defaulting contractor. This clause, no doubt, gives further right to the Department to blacklist thecontractor for a period of 4 years and also forfeit his earnest money/ security deposit, if so required. It is thus apparent that this sub-clause provides for various actions which can be taken and penalties which can be imposed by the Department. In such a situation which action the Department proposes to take, need to be specifically stated in the show cause notice. It becomes all the more important when the action of black listing and/ or forfeiture of earnest money/ security deposit is to be taken, as the clause stipulates that such an action can be taken, if so warranted. The words “if so warranted”, thus, assume great significance. It would show that it is not necessary for the Department to resort to penalty of black listing or forfeiture of earnest money/ security deposit in all cases, even if there is such a power. It is left to the Department to inflict any such penalty or not depending upon as to whether circumstances in a particular case warrant such a penalty. There has to be due application of mind by the authority competent to impose the penalty, on these aspects. Therefore, merely because of the reason that Clause 27 empowers the Department to impose such a penalty, would not mean that this specific penalty can be imposed, without putting the defaulting contractor to notice to this effect.