Pradip Kumar Gupta v. Union of India and Ors.
Case brief
What is this about?
Maintainability of writ petition in contractual matters under Article 226; Joshi Technologies International Inc. v Union of India (2015) 7 SCC 728 paras 69-70.11; Unitech Limited v Telangana State Industrial Infrastructure Corporation (2021) 16 SCC 35 para 38; ABL International Ltd v Export Credit Guarantee Corporation (2004) 3 SCC 553; promissory estoppel against Government; Kaniska Trading v Union of India (18 October 1994); termination of existing parcel-space lease operator; ICF to LHB rake conversion; HQ/ER Letter No. C. 375/Parcel Policy/FM/25/dated 20.02.2025; Train No. 13509 ASN-Gonda; Front SLR (2) / FSLR-II lease; fresh tender during subsisting agreement; arbitrariness and unreasonableness; restraint on giving effect to tender; WPA 2028 of 2026 interim order dated 12.02.2026; contract expiry 18.3.2027.
What did the court decide?
Railways restrained from giving effect to the new tender so long as the existing agreement (ending 18.3.2027) remains in force, though free to continue the tender process; directed to allow the highest bidder as per the existing agreement to operate Contract No. 13509-SLR-F-2-ASN-GD until expiry of term; interim order in WPA 2028 of 2026 declared no bar for FSLR-related decisions; allegations deemed not admitted since no affidavit called for; writ petition disposed of.