Nityadhara Tradelink Pvt. Ltd. v. Moslem Molla; CO No.3488 of 2025 (decided 21.11.2025, Shampa Sarkar, J.); civil revision against ex parte ad interim injunction in Misc. Appeal No. 60 of 2025 arising from Title Suit No.619 of 2025, Baruipur; urgency requirement for ad interim injunction; appellate court should not reverse reasoned trial court refusal; conflict of land records - latest land record prevails; L.R. record rebuttable presumption of possession; deeds of 1963/1966 chain of title; sanction plan construction permitted; RERA-registered project; injunction application remitted to trial court with two-month timeline.
What did the court decide?
Order dated August 30, 2025 passed in Misc. Appeal No. 60 of 2025 set aside; construction permitted on the portion exclusively under construction as per the sanction plan; Misc. Appeal disposed of as nothing remains to be decided; objection to the injunction application to be filed within a fortnight from communication of the order and the learned trial judge requested to dispose of the injunction application within two months thereof, independently; all steps taken in the interregnum by the defendants to abide by the final decision of the learned trial judge; no order as to costs.