M. Ravi v. the Superintending Engineer and Anr.
Case brief
What is this about?
Keywords: power supply connection; unanswered representation dated 17.10.2023; Electricity Department, Port Blair/Andaman; writ petition WPA; direction to dispose representation within seven days; administrative delay; parties to act on server copy. No statute sections or precedent citations appear anywhere in the judgment; statutes_cited and cases_cited are empty. Short single-judge mandamus-type disposal, useful for petitions seeking action on representations pending with electricity authorities.
What did the court decide?
Direction to the respondent authorities to dispose of the petitioner's representation dated 17 October 2023 within seven days from communication of the order; the order to be communicated by 5 February 2024. ¶14