Najrul Sekh v. Jelehar Begum and Anr.
Case brief
What is this about?
The High Court of Calcutta modified the impugned order in a partition suit appeal. The court directed site verification by officials to allow construction on the site of a demolished thatched house and mandated disposal of the suit within 18 months with a preliminary decree in 12 months.
What did the court decide?
Impugned order modified; site verification directed; suit must be disposed within 18 months with preliminary decree in 12 months; joint report due by 31st January 2023.