Baburao Sahebrao Deshmukh v. State of Maharashtra, through Collector, Washim and Another
Case brief
What is this about?
Writ petition allowed; withholding of contractor's security deposit of Rs. 38,46,413/- (including Rs. 25 lakh from running bills) by Municipal Council, Washim held unjustified. Monorail with track and platform construction in temple garden, Washim; work awarded 22/09/2017; Chief Officer letter 10/10/2018 recorded completion; third party audit by Government Polytechnic College, Washim dated 16/09/2020 certified completion; audit report dated 25/07/2025 noted only unfruitful expenditure of Rs. 1.22 lakh and did not find work incomplete; inquiry against then Chief Officer not a ground to withhold contractor's dues; no forfeiture under agreement clause; simple interest at 6% per annum till realization; no order as to costs; Bombay High Court, Nagpur Bench; 2026:BHC-NAG:4440-DB.
What did the court decide?
Writ petition allowed; respondent No.2-Municipal Council, Washim directed to pay Rs. 38,46,413/- (security deposit including Rs. 25 lakh deducted from running bills) with simple interest at 6% per annum from the date the amount became due and payable till realization; no order as to costs; writ petition disposed of in above terms.