Shyam Ganga Infra LLP Thr. Its Partner, Pravin Shyamdeoraoji Raut, Nagpur v. State of Maharashtra, Thr. Secretary of Urban Devpt. Dept., Mumbai and Ors.
MRTP Act 1966, ss.127(1) & 127(2) – Lapse of reservation
Case brief
What is this about?
Lapse of land reservation; Section 127 MRTP Act 1966; purchase notice; 24-month period; deemed release from reservation; defective purchase notice defence rejected; K Prat; Akhiv Patrika; title or interest document only; TDR offer not a step towards acquisition; TDR/FSI agreement requirement; Nagpur Improvement Trust; Nagpur Municipal Corporation; State of Maharashtra Urban Development Department; Shyam Ganga Infra LLP; Kh. No.198/1 Mouza Zingabai Takli Nagpur; Reservation MNS-96 NIT Office 4550 sq.m.; Revised Final Development Plan Nagpur; Yakub Salebhai Contractor WP 13965 of 2024; Shri Vinayak Builders Full Bench 2022 (4) Mh.L.J. 3739; right to develop land; Official Gazette notification of lapse; 2026:BHC-NAG:5280-DB.
What did the court decide?
Declared that the reservation for 'NIT Office' vide Reservation No. MNS-96, area admeasuring 4550 sq. mtr., in the Revised Final Development Plan, affecting land bearing Kh. No.198/1 of Mouza Zingabai Takli, Tq. & Dist. Nagpur, has lapsed under Section 127 of the MRTP Act; petitioner declared free to develop the land as permissible for adjacent land per the Development Plan; concerned respondent directed to publish in the Official Gazette, within eight weeks, the notification of lapsing of reservation under Section 127(2); Rule made absolute; no order as to costs.