Balasaheb Eknath Charvad Prop M/S Tejas Construction v. the Competant Authority / District Deputy Registarar Pune City and Anr.
Case brief
What is this about?
Adjournment/stand-over order continuing interim relief. Keywords: Bombay High Court Appellate Side Civil Jurisdiction; WRIT PETITION NO. 4081 OF 2024; WP 4082/2024; WP 4083/2024; Balasaheb Eknath Charvad; M/s Tejas Construction; Competant Authority District Deputy Registarar Pune City; Justice Somasekhar Sundaresan; S.O. to 22/01/2026; ad-interim interim relief continuation; Adv. Sayali Apte; Anjali Maskar; P. G. Lad; AGP A. A. Nadkarni; M. S. Srivastav; M. S. Snehal S. jadhav; Registrar Judicial-I.
What did the court decide?
Stand over (S.O.) to 22/01/2026; ad-interim or interim reliefs operative until 06-01-2026 to continue until the next date; reliefs not granted for a limited period remain unaffected. ¶¶23