Sunil Pandurang Lokhande v. the State of Maharashtra Thru. U.D. Dept and Anr.
Case brief
What is this about?
unauthorized construction; Pimpri Chinchwad Municipal Corporation; Planning Authority; building permission; co-owner consent; Survey No.201/1; Green Hills Burde Vasti; representations to Commissioner; demolition inquiry; competent Civil Court adjudication; 7x12 extract; Bhau Bhagoji Raskar heirs; Shankar Vitthal Raskar; Vitthal Bhau Raskar; Jankabai Gopal Burude; directions to Municipal Commissioner; 12 weeks timeline; stay order by Civil Court; Bombay High Court writ petition disposed
What did the court decide?
Respondent No.2 directed to take an appropriate decision on the two representations dated 18th August 2025 and 7th October 2025 within a period of 12 weeks from communication of the order, after hearing the concerned parties; Petitioner directed to communicate the order to Respondent No.2; Respondent No.2 at liberty to take action only after considering whether any legal impediment, including any stay order by the Civil Court, is involved.