Aslam Jilani Chaus v. the Project Director National Highway Authority of India and Others
Land acquisition – National Highways Act, 1956 – Sections 3G(1), 3G, 3H(4)
Case brief
What is this about?
Keywords: National Highways Act 1956 S.3G / S.3G(1) / S.3H(4); NHAI land acquisition compensation; owner's name omitted from award; zero compensation in e-statement; re-measurement mismatch; Gazette notification dated 22.05.2020; award dated 22.06.2022 set aside; direction to pass fresh award within three months; National Highway No.211 expansion, Dharashiv/Osmanabad; Article 226 writ; Bombay High Court, Aurangabad Bench, Writ Petition No. 14060 of 2025; decision dated 05.02.2026; per Hiten S. Venegavkar, J.
What did the court decide?
Writ petition allowed; award dated 22.06.2022 passed by respondent No.3, to the extent it relates to the petitioner, set aside; respondent No.3 directed to consider the notification dated 22.05.2020 and pass a fresh award under Section 3G of the National Highways Act, 1956 after complying with the prescribed procedure, within three months.