Devi Constructions LLP v. State of Maharashtra Thr the Industries Energy and Labour Dept. and Ors.
Case brief
What is this about?
Wind-energy refund dispute: Devi Constructions LLP sought 50% refund of expenditure on the power evacuation facility for WTG S-17 at Sadawaghapur Substation (Taluka Patan, Dist. Satara) plus 12% simple interest. With the amount undisputed at Rs.21,87,500/- (GR dated 11.02.2026), the sole issue was the payee - the Green Energy Fund/MEDA route to Promoter Respondent No.6 Suzlon Energy Ltd (deleted as party on 22.01.2026, having never objected) versus direct payment. Held: Respondent No.3 to pay Rs.21,87,500/- directly to the Petitioner within 15 days of uploading the order; no interest; no costs; compliance on 05.05.2026. References: Clause 3.02.5, GOM Non-Conventional Power Generation Policy 2008; Clause 25, GOM Non-Conventional Power Generation Methodology 2010; Maharashtra Energy Development Agency; Suzlon Energy Ltd.
What did the court decide?
Respondent No.3 (Maharashtra Energy Development Agency) to refund Rs.21,87,500/- directly to the Petitioner within 15 days of the order being uploaded on the High Court website; no interest payable; no order as to costs; Writ Petition placed on Board for reporting compliance on 5th May 2026.