The Police Officers Progressive Co-Operative Housing Society Ltd. v. Gurupratap Gandhi and Ors.
Case brief
What is this about?
Condonation of delay; 99 days delay; sufficient cause; co-operative housing society; concurrence of members for further litigation; erroneous belief that limitation was 90 days; 30-day limitation period learnt on legal advice; deliberations amongst 31 members; stay application after certified copy rejected; Interim Application No. 8104 of 2025; First Appeal (ST) No. 11839 of 2025; High Court of Judicature at Bombay; Civil Appellate Jurisdiction; Sharmila U. Deshmukh, J.; interim application allowed; appeal admitted; record and proceedings called; notice waived.
What did the court decide?
Delay of 99 days in filing the appeal condoned; Interim Application No. 8104 of 2025 allowed; First Appeal (ST) No. 11839 of 2025 admitted; Record and Proceedings directed to be called; Mr. Joshi waives notice for the Respondents. ¶4