Future Generali India Insurance Company Limited v. Reliance General Insurance Company Limited
Case brief
What is this about?
Interim Application No. 6606 of 2025 in Commercial Suit No. 1341 of 2018; Future Generali India Insurance Co. Ltd. (Applicant) v. Reliance General Insurance Co. Ltd. (Defendant); Bombay High Court, Ordinary Original Civil Jurisdiction; Somasekhar Sundaresan J.; order dated February 27, 2026; joint insurance of a risk; re-insurance contract; proposed Defendant No. 2 as necessary party; service pending four years; framing of issues not to be held up; liberty to frame further issues on Defendant No. 2 joining; matter listed March 10, 2026 “For Framing Issues”; counsel: Pranav Sampat, Rashika Bajpai, Mannat Gupta (Khaitan & Co.) for Applicant; Rohan Kadam, Nafisa Khandeparkar, Ashutosh Desai (AZB & Partners) for Defendant.
What did the court decide?
No hold-up of framing of issues; liberty to frame further issues as and when Defendant No. 2 joins the proceedings; matter stood over to March 10, 2026 under caption “For Framing Issues”; all actions under the order to be taken upon receipt of a downloaded copy from the Court’s website.