Infrastructure Logistics Systems Pvt. Ltd. v. District Deputy Registrar Co-Operative Societies Mumbai III and the Competent Authority
Case brief
What is this about?
Section 80(1) CPC notice; waiver of two-month statutory waiting period; leave to institute suit against District Deputy Registrar Co-operative Societies Mumbai III and Competent Authority; prior knowledge of respondent; Civil Writ Petition Nos. 2027, 2022, 2025 of 2016; common order dated 1st October 2025 granting ten weeks' liberty; suit instituted pursuant to writ liberty; respondent served but non-opposing; Bombay High Court OOCS interim application; Infrastructure Logistics Systems Pvt Ltd.
What did the court decide?
Leave granted to the Applicant to institute the suit against the Respondents without serving the formal notice required under Section 80(1) of the CPC, and waiver of the statutory two-month waiting period, in terms of prayer clauses (a) and (b); no costs. ¶order-i