The Executive Engineer Medium Project Division Osmanabad District Osmanabad v. Mrs Soajr Wo Sampat Mane and Ors.
Case brief
What is this about?
Bombay High Court, Aurangabad Bench; Shailesh P. Brahme, J.; decided 09.03.2026; First Appeals Nos. 2238-2244 of 2024 with connected Civil Applications; land acquisition compensation enhancement; interest dates under Sections 23, 28, 29 and 34 of the Land Acquisition Act; interest under Sections 28/34 from date of award (State of Maharashtra v. Kailash Shiva Rangari, 2016 AIR (Bom.) 141) versus date of Section 4 notification; interest under Section 23 from date of Section 4(1) notification per Kolkata Metropolitan Development Authority (Supreme Court); Lower Khairi Brahat Minor Percolation Tank, Osmanabad; LAR Nos. 502/2012, 430/2012, 496/2012, 497/2012, 498/2012, 500/2012, 501/2012; notification 08.03.2001; award 14.01.2008; error of jurisdiction by Reference Court; appeals partly allowed.
What did the court decide?
Paragraph no. 4 of the operative part of the Reference Court's judgment and award modified so that interest under Section 28 and 34 of the L.A. Act is payable from the date of the award (as per State of Maharashtra v. Kailash Shiva Rangari); the rest of the impugned judgment and award left unaltered; undisbursed amounts with interest to be disbursed to the respondents/claimants; pending Civil Applications disposed of.