Darshan Vinod Gangwal v. M/S. Konkan Agro Marine Industries Pvt. Ltd. and Others
Case brief
What is this about?
Summary suit; leave to defend; Order 37 CPC; conditional leave; deposit into court; bank guarantee; sub-standard goods; bagasse supply; fuel contract; triable issue; plausible defence; IDBI Trusteeship v Hubtown paras 17.3 and 17.4; admitted amount; second proviso Rule 3(5); laboratory report; debit note; commercial recovery; Aurangabad Bench; written statement timeline; Oriental Aromatics distinguished.
What did the court decide?
Civil revision application rejected (substantially); respondents/defendants directed to further deposit Rs.15,00,000/- or furnish bank guarantee to that extent within four weeks, to file written statement within eight weeks, and to cooperate with the Trial Court, failing which adverse action may follow. ¶18