The President of India through Chief Engineer (Construction )/Cpm/Ngp Central Railway v. Kec International Ltd.
Case brief
What is this about?
Section 34 Arbitration and Conciliation Act 1996 — patent illegality; re-writing of contract; conversion of lump-sum EPC contract into item-wise/item-rate contract; change of scope Article 13.1.2 vs mere variation in quantity of earthwork; valuation per Clause 13.2.3; Article 2.1 exhaustive 'means and includes' Scope of Project; Article 3.8 unforeseeable difficulties — contractor's responsibility, no price/time adjustment; Schedule B clause 1.3.10.1 — no claim for lack of foresight of site conditions; Article 5.2 representations and warranties silent on data accuracy; appointed date refixation to 04-10-2023; 84.3% Right of Way; Article 8.2.1 joint inspection/memorandum as valid evidence of ROW hand-over; joint notes 01-10-2022 and 16-02-2023; Article 8.3.1 damages formula 0.10 x C x 1/L x 1/N; 368 days delay; Article 10.4.5 continuing-event interim claims; standing arbitral tribunal; Article 21.1.2 termination invalid without enforceable default notice — default notice 07-03-2024 stayed by Tribunal order 08-05-2024 (Section 17 application); severability of arbitral award — Prayer C and D quashed, balance confirmed; Section 34(2A) 'the Court finds that' — State of Chhattisgarh v Sal Udyog (2022) 2 SCC 275; Union of India v Susaka (2018) 2 SCC 182; NBCC v Sharma Enterprises (2025) SCC Online Del 8505; OPG Power Generation v Enexio (2025) 2 SCC 417; PSA Sical Terminals (2023) 15 SCC 781; KEC International Ltd v President of India/Central Railway — third railway line Itarsi-Nagpur (Maramjhiri-Chichonda), 69.80 km, Rs 536.23 crores; Bombay High Court Commercial Division; Justice Sharmila U. Deshmukh; 2026.