Nutan Builders v. Uma Smruti Co-Operative Housing Society Limited
Case brief
What is this about?
Section 37 Arbitration and Conciliation Act 1996 appeal; Bombay High Court Commercial Division; Commercial Arbitration Petition No. 3 of 2025 with Interim Application (L) No. 17312 of 2023; Nutan Builders (petitioner, counsel Tushar Goradia) v. Uma Smruti Co-Operative Housing Society Limited (respondent); disposed of as infructuous; underlying arbitral proceedings concluded; single-judge bench of Somasekhar Sundaresan J.; decision date January 17, 2026.
What did the court decide?
The Petition filed under Section 37 of the Arbitration and Conciliation Act, 1996 was disposed of as infructuous, the learned Advocate for the Petitioner having stated that the underlying arbitral proceedings have come to an end. ¶¶10