Generic Engineering Construction and Projects Ltd. v. Maharashtra Maritime Board
Case brief
What is this about?
Appointment of arbitrator Section 11 A&C Act; existence of arbitration agreement; arbitrability of contract termination; Dispute Review Expert not nominated; Clause 24/25 GCC vs Clause 36 Contractor's Bid vs Clause 3 SCC; Clause 2.3 GCC order of priority; deletion of SCC 3.1-3.3; CEO termination decision outside 'Engineer' clause; exhaustion of pre-arbitration procedure; Maharashtra Maritime Board BKC office building; Section 9 converted to Section 17; pro-arbitration reading of conflicting clauses; distinguished Mehra & Co. and B.T. Patil; relied on Visa International, Quick Heal Technologies, NPCCL (Calcutta HC); Bombay High Court Commercial Arbitration Petition 2026.
What did the court decide?
Smt. Justice Anuja Prabhudesai, former Judge of the Bombay High Court, appointed as Sole Arbitrator for disputes arising out of the contract/agreement dated 6 February 2023; Section 9 Petition (CARBP-1070 of 2025) converted into Section 17 application before the Arbitral Tribunal; all rights and contentions of the parties kept open.