Kundatai Ramchandra Mahajan and Others v. the Collector (Land Acquisition) Pench Project, Nagpur
Case brief
What is this about?
Condonation of delay 744 days; restoration of first appeal refused for office objections; Registrar (Judicial) order dated 24.01.2023; cost Rs. 7,000 to Public Welfare Account; CAO No. 94 of 2026 in FA(ST) No. 12036 of 2021; Misc. Civil Application (ST) No.4804/2025; remove office objections within one week; land acquisition Pench Project Nagpur; single judge Prafulla S. Khubalkar; Nagpur Bench; order dated 11.02.2026.
What did the court decide?
Delay of 744 days in filing the restoration application condoned subject to payment of Rs. 7,000/- cost to the 'Public Welfare Account'; Civil Application (CAO) No. 94 of 2026 allowed and disposed of. Companion Misc. Civil Application (ST) No.4804/2025 for restoration of First Appeal (ST) No. 12036 of 2021 allowed, with directions to remove office objections within one week, after which the appeal is to be registered.