Nilkanth Baburao Ingale and Anr. v. the Executive Engineer, Osmanabad Minor Irrigation Division, Osmanabad and Ors.
Case brief
What is this about?
Nilkanth Baburao Ingale; land acquisition compensation; First Appeal No. 239/2018; Civil Application No. 4904 of 2026; withdrawal of award deposit 75% with interest; undertaking against 50% withdrawal; solvent surety/security against 25% withdrawal; Registrar (Judicial); remaining 25% in Fixed Deposit Nationalized Bank two years; Reference Court enhancement to Rs.7500/- per Are (LAO rate Rs.800/- per Are); Executive Engineer Osmanabad Minor Irrigation Division; reliance on order dated 09.03.2026 in Civil Application No. 2687/2026 in First Appeal No. 849/2026; interim withdrawal during pendency of appeal; Neeraj P. Dhote; Aurangabad Bench, High Court of Bombay.
What did the court decide?
Withdrawal of 75% of the amount under the Award deposited by the Acquiring Body, with accrued interest — subject to an undertaking against withdrawal of 50% and solvent surety/security against withdrawal of 25%, to the satisfaction of the learned Registrar (Judicial) — with the remaining 25% and interest to be kept in fixed deposit in a Nationalized Bank initially for two years; the Application stands disposed of.