The Maharashtra Krushna Valley Development Co. Thr Ex. Engineer, Medium Project Osmanabad and Ors. v. Gokul Vishwanath Shinde and Anr.
Case brief
What is this about?
Aurangabad Bench procedural order condoning a 1215-day delay and restoring First Appeal (ST) Nos. 5258/2022 and 5237/2022 (reference-court/land-acquisition appeals involving Maharashtra Krushna Valley Development Corporation and applicants Balasaheb Vishwanath Shinde and Gokul Vishwanath Shinde); setting aside the Court's order dated 18.10.2022; impleadment of Applicant No. 2 omitted due to error corrected before the Reference Court; permission to withdraw 75% of the deposited amount with accrued interest on undertaking to Registrar (Judicial); admission of both appeals; waiver of service by Mahesh B. Kale; advocates Mahesh P. Kale, Akash Rodge, Anil M. Gaikwad, D. S. Jape (AGP).
What did the court decide?
Delay of 1215 days condoned and the order dated 18.10.2022 passed by this Court set aside (CA Nos. 2502/2026 and 2388/2026, prayer clauses (A) and (B)); F.A. (St.) Nos. 5258 of 2022 and 5237 of 2022 restored and thereafter admitted; Applicant No. 2 impleaded as party-respondent (CA No. 1358/2026, prayer clause (B)); applicants permitted to withdraw 75% of the amount deposited by the respondents with accrued interest on furnishing undertaking to the satisfaction of the Registrar (Judicial) (CA No. 1359/2026).