Amrut Sudhakar Narvekar and Ors. v. the Collector Sindhudurg and Ors.
Case brief
What is this about?
Enforcement of Maharashtra Pollution Control Board closure order dated 13-07-2021; disconnection of water and electricity to M/s. Balraje Fiber and Boat Builder; alleged illegal construction on suit property; inaction by Collector, Sindhudurg and Tahsildar despite notice dated 20-01-2020 and communication dated 20-10-2020; writ petition disposed of with two-month demolition direction; liberty reserved to petitioners. No statute or precedent cited in the order.
What did the court decide?
Direction to the official respondents to conclude the process of demolition of the subject structure, if found illegal, within two months; petitioners at liberty to approach the Court if their grievance survives. ¶21