Suryakant Gajanan Swami v. the State of Maharashtra through Its Secretary and Ors.
Case brief
What is this about?
Enhanced compensation; land acquisition compensation quantum; Inam land; Devasthan land; Gat No. 346 Daphalapur Tal. Jath Dist. Sangli; RFCTLARR Act 2013; representation dated 19.01.2022 and notice dated 18.12.2021 to Sub-Divisional Officer Jath undecided; direction to respondent nos. 2 to 5 to decide within 16 weeks; opportunity of hearing with legal assistance; entitlement left open; all contentions kept open; Bombay High Court Kolhapur Circuit Bench; Writ Petition 7868 of 2024; M. S. Karnik & Ajit B. Kadethankar JJ.; 13.11.2025; disposed.
What did the court decide?
Respondent nos. 2 to 5 directed to decide the representation within 16 weeks; petitioner permitted to resubmit a comprehensive proposal/representation with additional documents; decision to follow after hearing with liberty of legal assistance; claim to be decided on its own merits with all contentions kept open.