Bhalchandra Suresh Tilave v. Maharashtra State Electricity Distribution Company Ltd. (M.S.E.D.C.L.)
Case brief
What is this about?
Bombay High Court (Appellate Side, Civil Jurisdiction), Writ Petition No. 7850 of 2024: Bhalchandra Suresh Tilave (petitioner) v. Maharashtra State Electricity Distribution Company Ltd. / MSEDCL (respondent); single Bench of Ms. Justice Gauri Godse; order dated 11-07-2025. Procedural stand-over only: Balance Daily Board not taken up due to paucity of time; next date 07/11/2025; existing ad-interim/interim relief to continue till next date, and relief not limited in period to remain unaffected. No substantive adjudication, no ratio, no statutory or precedent discussion.
What did the court decide?
Matter stood over to 07/11/2025; any ad-interim/interim relief operating till then was to continue till the next date, and any such relief granted not for a limited period was to remain unaffected. ¶10