Sham S/O. Sheshrao Mate v. State of Maha., Thr. Collector, Buldhana and Others
Bombay High Court (Nagpur Bench), Khubalkar J: Land acquisition – reference of title dispute – Section 76, RFCTLARR Act 2013
Case brief
What is this about?
Keywords: Section 76 RFCTLARR Act 2013; Section 64 reference to Authority; Section 53 Authority/Tribunal composition; Section 63 bar; Land Acquisition Tribunal Nagpur; Collector cannot self-adjudicate entitlement dispute; rival sale-deeds Gat No.51; 7/12 extract and Form 8A not conclusive; Order VII Rule 11 CPC rejection; Vinod Kumar v. District Magistrate, Mau (2023) 19 SCC 126; Shrikrushna Shivshankar Chambhare WP 6218/2022 (DB); Mahadev Sukhdeo Rokade WP 5181/2022 distinguished; interim restraint on disbursal; direction to deposit compensation; perversity in ignoring pending civil suit and appeal. Relevant for: disputes over entitlement/apportionment of land-acquisition compensation, mandatory reference under Section 76 despite mutation entries and possession, quashing of LAO orders refusing reference.
What did the court decide?
Writ petition allowed and rule made absolute: order dated 30.12.2024 of respondent no.2 quashed and set aside; application dated 08.07.2024 for reference allowed and the dispute referred to the Land Acquisition Tribunal, Nagpur; respondent no.2 to secure and retain the compensation amount during pendency of the reference, if necessary by directing respondent no.3 to deposit it; no order as to costs.