M/S Unilab Chemicals and Pharmaceuticals Pvt. Ltd. v. Maharashtra Industrial Development Corporation and Ors.
Case brief
What is this about?
Unilab Chemicals v MIDC, Bombay HC WP 5891/2024, 24 Feb 2025, Art 226; MIDC additional premium and penalty demand for Building Completion Certificate (BCC)/Occupation Certificate quashed; demolition permission dated 18 Sept 2019 clause 11 – 36 months from 100% demolition; Covid-19 time-extension circulars 24 May 2021 and 29 Dec 2021 (18 Sept 2021 to 17 Jan 2023); petitioner assignee of Blue Rock Dyes & Chemicals/Chromatic India via deed dated 24 Apr 2019; impugned letters 17 Apr 2023 and 15 Dec 2023 untenable; fresh consideration of representations 1 Jan 2024 and 7 Jan 2024 by 12 Mar 2025; no costs.
What did the court decide?
Impugned communications dated 17 April 2023 and 15 December 2023 quashed and set aside; respondents directed to consider the petitioner's representations dated 1 January 2024 and 7 January 2024 (Exhibit 'S') afresh in light of the observations and pass an order on or before 12 March 2025; copy of order forwarded to MIDC; petition disposed of, no costs.