Satiate Engineering (I) Pvt. Ltd. Represented by Its Director v. the Board of Directors of Axis Bank Ltd. Represented by Its Managing Director
Case brief
What is this about?
Interim order, Bombay High Court. Keywords: interim injunction; NPA classification (31.12.2021); Magistrate Palghar order dated 28.08.2023; Tahsildar Palghar possession notice dated 10.11.2025; possession fixed for 28.11.2025; Supreme Court status quo order dated 10.09.2024; statements/undertakings accepted — Tahsildar instructed not to take possession; Axis Bank (Respondent Nos. 1-2) not to precipitate matter till disposal of Writ Petition; IA disposed; Writ Petition listed for admission-stage hearing on 16.12.2025 (High on Board); reference to M/s. Ray Projects Pvt. Ltd. v. Board of Directors of Canara Bank (Bom HC, order pronounced 07.10.2025). Parties: Satiate Engineering (I) Pvt. Ltd. (Petitioner); The Board of Directors of Axis Bank Ltd. & Ors. (Respondents).
What did the court decide?
Interim Application disposed of on the strength of statements accepted by the Court: (i) the Tahsildar, Palghar instructed not to take possession of the properties under the possession notice dated 10 November 2025; (ii) Respondent Nos. 1 and 2 not to precipitate the matter qua the said notice and/or taking of possession of the properties mentioned therein till the disposal of the Writ Petition; (iii) the Writ Petition to be placed for hearing at the admission stage on 16 December 2025, High on Board.