M/S. Patel Developers v. City and Industrial Development Corp. of Maharashtra Ltd. and Ors.
Case brief
What is this about?
CIDCO lease agreement termination withdrawn — Bombay HC disposes W.P. 5279/2025 (ION Infrastructure) and W.P. 5472/2025 (Patel Developers) after CIDCO states it will withdraw termination order dated 01.04.2025 and lease-termination proceedings, being bound by ad-interim injunction dated 27.11.2019 in Appeal from Order No. 39 of 2017 (filed by respondent no. 3); plea that cancellation for failure to develop plots was arbitrary not adjudicated; no costs or quantum; rule made returnable forthwith and heard finally by consent.
What did the court decide?
The writ petitions were disposed of on the record of CIDCO's statement that, being bound by the ad-interim injunction in Appeal from Order No. 39 of 2017, it had decided to withdraw the proceedings initiated for termination of the petitioners' leases as well as the impugned order dated 1st April 2025. No adjudication on merits.