Ai-Gausiya Kanduri Welfare Associateion v. the Chief Officer Mumbai Building Repairs and Reconstruction Board and 10 Ors.
MHADA – Mumbai Building Repairs & Reconstruction Board – Section 91A, MHADA Act 1996 – order of Chief Officer dated 22.04.2025 on tenants' application
Case brief
What is this about?
Section 91A MHADA Act; Chief Officer's order quashed for lack of reasons; transit rent Rs. 110 crores; Covid-19 default; PDCs; Commencement Certificate within one month; cluster redevelopment; Kathawala Realtors LLP v. Chief Officer, Mumbai Building Repairs & Reconstruction Board (MHADA Unit); Bombay High Court; writ petitions and contempt petition disposed.
What did the court decide?
Impugned order dated 22 April 2025 quashed and set aside; owner-developer permitted to continue the cluster redevelopment on undertakings (commercial premises within 24 months and residential redevelopment within 42 months from the Commencement Certificate); balance transit rent to be paid via PDCs issued to remaining tenants within 10 days and honoured; Commencement Certificate to be issued within one month of the application; all contentions of the tenants kept open; connected writ petitions and the contempt petition disposed of; no costs.