Power of One Logistics Park Private Limited v. Maharashtra Industrial Development Corporation
Case brief
What is this about?
W.P. 4633/2024, High Court of Bombay, disposed 02.04.2025 (Aradhe CJ & Karnik J). MIDC delay penalty Rs.69,44,281.34 (circular 07.06.2019) and extension charges Rs.5,89,98,585/- for Plot No.C-31, Talegaon Industrial Estate; gas pipeline on Plot No.C-32; Article 226 disputed questions of fact not decided summarily; Joshi Technologies International Inc. (2015) 7 SCC 728 para 70.3 relied on; petitioner directed to civil suit; refund with 12% interest sought, not granted. Counsel-cited (referred): ABL International (2004) 3 SCC 553; Surya Construction (2019) 16 SCC 794; MP Power Management (2023) 2 SCC 703; Gujarat Maritime Board (2016) 10 SCC 46. Statutes: MIDC Act 1961; Companies Act 1956; Article 226 Constitution.
What did the court decide?
No monetary relief granted: recovery not quashed, no refund or interest ordered. Petitioner given liberty to pursue the remedy of a civil suit against MIDC.