Brihanmumbai Municipal Corporation v. Union of India
Case brief
What is this about?
Brihanmumbai Municipal Corporation; Storm Water Drain; RCC retaining wall; NL Complex Nall; Dahisar (West); R/North Ward; flood management; mangroves; mangrove buffer zone; 50 meters; CRZ-I; CRZ Notification 2019 dated 18/01/2019; clause 7(iii); CRZ Notification dated 06/01/2011; MCZMA; 162nd Meeting 07/12/2022; SEIAA; MOEFCC; Ministry of Environment Forest and Climate Change; Union of India; Article 226; PIL No.87/2006; Para 83(viii); Judgment and Order dated 17/09/2018; writ petition disposed; liberty reserved; Bombay High Court; Alok Aradhe CJ; Bharati Dangre J; 7 February 2025.
What did the court decide?
No approval granted to the project. Writ Petition disposed of, with liberty reserved to the Petitioner to take appropriate steps as per law; Petitioner directed to obtain necessary approvals from SEIAA or MOEF&CC as contemplated under the CRZ Notification dated 06/01/2011 (as amended from time to time).