Ananda Datta Totawad v. the State of Maharashtra through Its Secretary and Others
Case brief
What is this about?
Bombay High Court, Aurangabad Bench; coram Manish Pitale & Y. G. Khobragade, JJ.; order dated 04.08.2025; omnibus adjournment of multiple writ petitions (e.g., WP 11627/2021, WP 2715/2023, WP 15432/2019, WP 193/2025) and PILs (24/2014, 37/2020, 31/2023, 53/2024, 9/2017, 27/2023 etc., with connected CAs) to dates 24.09.2025–06.10.2025; directions to remove office objections, file reply/rejoinder affidavits; ad-interim orders to continue. No merits adjudication, no statute or precedent discussed.
What did the court decide?
Adjournment of the listed writ petitions and PILs to scheduled dates between 24.09.2025 and 06.10.2025, subject to removal of office objections and filing of affidavit-in-reply/rejoinder before the next date, with existing ad-interim orders continuing until then. ¶22