M/S. George Developers Thr. Partner Santosh Markose George v. the Nagpur Improvement Trust, Thr. Chairman and Others
Case brief
What is this about?
WP 396/2024; 2025:BHC-NAG:8779-DB; Bombay HC Nagpur Bench; George Developers v. Nagpur Improvement Trust; illegal construction; notice dated 18/4/2023; Gunthewari regularisation; Plot Nos. 27, 27A, mouza Zingabai Takli; building permission application dated 21/7/2025; 90-day direction; opportunity of hearing; all issues kept open; Rule made absolute; Jawalkar & Patil JJ.
What did the court decide?
Respondent No.1/Competent Authority of Nagpur Improvement Trust directed to decide Respondent Nos.3 and 4's building-permission application dated 21/7/2025 within 90 days from the parties' appearance before it, on merits with opportunity of hearing; Petitioner permitted to participate; all issues kept open; parties directed to appear before Respondent No.1 on 8th September, 2025; Rule made absolute in above terms; no order as to costs. ¶19